Distributed Renewable Energy

Net-Billing

If you want to benefit from solar energy by connecting your premises to the electricity grid and having excess energy credited to your bill to reduce costs and support renewable energy, this service is for you. It is provided under an agreement with a licensed engineering office.

Service Information

Service Information

Application Process

  1. Appoint an EWA-approved contractor and consultant to submit the application and required documents through the Benayat channel.
  2. The application is reviewed by EWA after consultant approval.

Service Fees

  • No Fees

Service Duration

  • 4 Working Days

Service Steps

  1. Assign Approved Contractor & Consultant
    Assign an EWA-approved contractor and consultant. Your contractor will submit your request along with the required documents through Benayat.
  2. Consultant Review
    Your consultant will review the submitted request and approve it through the platform.
  3. EWA Review & Inspection
    Once approved by your consultant, EWA will review your request and carry out a field inspection of your premises.
  4. System Connection
    After EWA’s final approval, your system will be connected to the electricity grid.
  5. Your Service is Complete